A sonar inspection conducted in 2022 revealed an average clogging rate of 40% on the northern branch of the intercommunal network, located near the Sports Park and Balizy Plain. This 1,400 mm diameter pipeline, nearly 1,200 metres long, received a significant flow of approximately 26,000 m3/day. To restore the hydraulic capacity of this strategic facility, SIAHVY and SUEZ teams launched a dry cleaning operation.
To minimise constraints on the collection basin, the operation was carried out at night during the summer period when flow is lowest. Drying the northern branch required daily operation of several valves and a ballasting-pumping system to divert effluents to the southern branch. The hardness of the accumulated sands and risks associated with hydrogen sulfide (H2S) presence made the interventions particularly demanding for the teams involved.
The cleaning, followed by a television inspection, took place in two phases: from July to October 2025 at the Sports Park (617 metres) and from July to early September 2026 at the Balizy Plain (580 metres). In total, the project required 600 man-nights, involved 210 truck rotations, and cost €1.22 million covered by the Public Service Delegation. SIAHVY President, Sandrine Gelot, Mayor of Longjumeau, and Bernard Texier, delegated vice-president for sanitation, visited the project site on September 1, 2026.